In any RCC (Reinforced Cement Concrete) project, whether it’s a villa in Electronic City, an apartment in Nagarabhavi, or residential construction in Bangalore, the quality of shuttering (also called formwork) plays a crucial role in shaping the structure—literally and figuratively.
Shuttering provides the mould for concrete to take its desired shape. Poor-quality shuttering and a lack of quality checks during concreting can lead to structural flaws, safety issues, and higher maintenance costs.
This article highlights:
- What shuttering is
- Key elements of good shuttering
- Quality checks to perform before concreting
- Do’s and don’ts for better RCC strength and durability

What Is Shuttering (Formwork)?
- Shuttering refers to the temporary or permanent mold into which concrete is poured and allowed to set. It defines the shape, alignment, and finish of RCC elements such as slabs, beams, columns, and foundations.
- Common Shuttering Materials:
- Plywood (marine-grade or film-faced)
- Steel plates (durable, reusable)
- Aluminum (lightweight, good for high-rise)
- Plastic (for modular and lightweight uses)
- Timber (used for small-scale or custom works)
Key Elements of High-Quality Shuttering

Strength & Rigidity
Should withstand concrete pressure without bending or bulging.
Accurate Dimensions
Ensures RCC elements meet design sizes and levels.
Leak-Proof Joints
Prevents slurry leakage, which causes honeycombing and weak spots.
Leak-Proof Joints
Prevents slurry leakage, which causes honeycombing and weak spots.
Smooth Finish
Affects the surface quality and plastering needed afterward.
Ease of Removal (Deshuttering)
Should be easily removable without damaging the concrete.

Essential Quality Checks Before Pouring RCC
Alignment & Plumb
- Check verticality of columns and straightness of beams.
- Use spirit levels, plumb bobs, or laser levels.
Tightness of Joints
- No gaps between panels to avoid slurry leakage.
Formwork Cleanliness
- Clear all debris, dust, or nails before pouring.
Application of Shuttering Oil
- Apply form oil to prevent concrete from sticking, improving finish and reducing damage during removal.
Supports & Props
- Ensure props are firm, plumb, and securely braced.
- Double-check in beam and slab areas where pressure is high.
Level & Dimensions
- Confirm beam depth, slab thickness, and column size per structural drawing.
Opening for Electrical & Plumbing
- Mark and place sleeves or boxes as per layout to avoid cutting RCC later.

Do’s:
- Use only approved materials (plywood, steel, etc.)
- Ensure tight joints to prevent slurry leakage
- Apply shuttering oil to all surfaces in contact with concrete
- Maintain minimum curing period after deshuttering
- Check for propping and bracing to prevent collapse
Don’ts:
- Don’t reuse damaged or warped plywood
- Don’t remove shuttering too early (wait 7–14 days depending on RCC element)
- Don’t pour concrete without checking shutter alignment
- Don’t allow water stagnation inside the formwork
- Don’t skip quality checks for props and centering

Deshuttering Time (as per IS 456:2000)
| RCC Element | Minimum Removal Time |
| Vertical formwork (columns, walls) | 16–24 hours |
| Slabs (props left under) | 3 days |
| Beams (sides) | 2–3 days |
| Slab props (up to 4.5m span) | 7 days |
| Beam props (up to 6m span) | 14 days |
These are guidelines. Always consult your structural engineer or construction company before removing shuttering.
Impact on RCC Durability Poor shuttering can lead to:
- Honeycombing
- Dimensional inaccuracies
- Surface cracks
- Water seepage and corrosion
- Reduced load-bearing strength
High-quality shuttering ensures:
- Structural accuracy and safety
- Better bonding and finishing
- Minimal plastering corrections
- Increased lifespan of RCC components
Where It Matters Most “Shuttering is crucial in”:
- Residential construction in Bangalore: floors, roofs, beams
- Villa construction in Electronic City: foundation and slabs
- Apartment towers in Nagarabhavi: lift cores, columns, walls
Even the best concrete mix (M20, M25, M30) and reinforcement will underperform without properly installed and checked shuttering.
Conclusion
When it comes to RCC construction, shuttering is the unsung hero that gives your structure its shape and strength. Ignoring it can lead to weak structures, cracks, and cost overruns.
Whether you’re working on residential construction in Bangalore or planning a premium villa project, focus on shuttering quality checks, follow the right do’s and don’ts, and ensure deshuttering is done with care.
Want a downloadable shuttering quality checklist for your site or team? Let me know—I’ll prepare one for you!